Project:
A1139 Orton Parkway Major Maintenance
Client:
Skanska | Highways England
Sector:
Highways
Completion:
2018
The Project
Local government major highways maintenance scheme to refurbish the busy A1139 Orton Parkway in Peterborough.
Our Work
Working during night shifts to minimise disruption, under full road closure we replaced 2.5km of surface course to a dual carriageway and two roundabouts – totalling 26,000 m2.
19,500 m2 of binder course was also replaced and 800m of crack repairs undertaken.
Working closely with our client, we were able to reduce the overall programme time by two laying shifts, completing the project ahead of time despite losing a full shift due to the weather.
Results & Achievements
- Minimum disruption to major road
- Reduced programme time
- On time, to budget
- Delivered Safely